What type of files can you import into P6 V 8.2 eg. Microsoft Project etc? 

3 replies

Oldest first
  1. 0
    Paul Harris ·

    P6 V8.2 Optional and

    P6 V8.2 Optional and Professional Client will import.

    • XER, which is Primavera's file type for importing and exporting
    • Primavera XML, similar to XER but only one project at a time may be imported,
    • P3
    • MSP XML format
    • MPP if you have only an earlier version of MSP, 2003 and earlier,  as later versions disable the MPP import
    • XLS

     

    P6 V8.2 Web will import

    • Primavera XML, similar to XER but only one project at a time may be imported,
    • MSP XML format
    • XLS

    Regards

    Paul E Harris

    Eastwood Harris Pty Ltd

    www.eh.com.au

    Primavera and Microsoft Project books and training manual publishers

  2. 0
    V Kutty ·

    Thanks Paul,

    Thanks Paul,

  3. 0
    Adam Goddin, PE, PMP ·

    Just remember, any column

    Just remember, any column with an asterick will not import back into the software.  I have been creating a user text, user integer or use rnumber column and importing things into it as a work around for some scenarios.  This works well for a limited number of items.  Does anyone understand the logic in the "Autocost Rules" for P6?  I have not found a concise definition of these rules written down.  Am I overlooking this information?  Thanks, Adam

     