ForeCast VS SoM

Yifei 87Member for 13 years 7 months
Created
4
2
0

Hi, I m new to p6 and encounter a question.

I m trying to do Foracast vs SoM.  However,  when I added the column, the list is empty.  I check that they are I have some activities which are Start Milestones and Finish Milestones.  However, for Milestones Date & SoM dates column, they are empty when I  add the column.

May I know why?  Can anyone assist me?

Thank you very much

4 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Hi Yifei,   Please could you

    Hi Yifei,

     

    Please could you tell me what "SoM" means?

    Also, please could you tell me exactly which date column you are adding, that is blank (there are approx. 30 different date columns available in P6)

  2. 0
    Yifei 87 ·

    Hi Gary,SoM Date should reder

    Hi Gary,

    SoM Date should reder to Schedule of Milestones Date which parked under user defined.

     

     

  3. 0
    Gary Whitehead ·

    Yifei,   You have to manually

    Yifei,

     

    You have to manually add data into User-defined fields yourself -They are not calculated by P6

     

    Cheers,

     

    G

  4. 0
    Yifei 87 ·

    IC. Thank You ver much.

    IC. Thank You ver much.  