Hi All,

How to get physical percentage complete to rollup upto my wbs and project level?

3 replies

Oldest first
  1. 0
    Daniel Limson ·

    Hi Vidhya,First off, you need

    Hi Vidhya,

    First off, you need to have a common unit of measure (Manhours, Mandays, Dollar or a Weighted Value) broken down to the activity level and loaded to your P6 programme.

    Cheers,

    Daniel

  2. 0
    Vidhya Sagar G R ·

    Hi Daniel,I am not using any

    Hi Daniel,

    I am not using any resource into my project.

  3. 0
    Daniel Limson ·

    Vidhya,You can use a time

    Vidhya,

    You can use a time base resource by using duration, however, it is not an accurate assessment of physical percentage complete.

    When you say physical percentage complete, it should be based on estimated quantities and then converting this to weighted value by using a common unit of measure time or money (Manhours, Mandays or Dollar Value).

    Cheers,

    Daniel