Resource Planned Value

Sneh KumarMember for 14 years 3 months
Created
2
1
0

Dear All,

In my schedule each activity has more than 5-6 resource assigned to it. For updating the actual, our discipline engineers want to know the planned value of each resource on the Datadate (for reference). I could able to get the overall palnned value but not able to get the planned value of each resource.

Is it possible to get the planned value of each resource on the datadate by running the schedule?

Please suggest. 

2 replies

Oldest first
  1. 0
    Alain De leon ·

    Hi sir/ma'amgo to resource

    Hi sir/ma'am

    go to resource usage spreadsheet, Highlight your sepecific resource, and customize your spreadsheeet field. hope it helps

    Godbless

  2. 0
    Andrew Podolny ·

    Hi Sneh.If your resource

    Hi Sneh.

    If your resource assignments share same calendar and connected to activity dates - you can refer to overall activity planned % on date. However if you are using resource assignments lags or different calendars the only way to get proper planned % for each assignment is to open your baseline and in resource assignments view calculate what % should be completed on data date. Primavera doesn't provide with planned % and all  EV - related data at resource assignments level.

    Regards,

    Andrew