Earned Value Labor Units

Abilash Palakkadan MathewMember for 14 years 1 month
Created
2
1
0

Hi Guys,

 

I have got a problem with Earned Value Labor Units in one of my projects new activities, that Earned Value Labor Units is not getting calculated according to activity %. Please suggest the possible reason, to fix this error.

 

Regards,

Abilash

2 replies

Oldest first
  1. 0
    Arnold Puy ·

    Hi Abilash,Earned Value Labor

    Hi Abilash,

    Earned Value Labor Units will be calculated based on Performance % Complete. Try the following that might fix the issue.

    1. Make sure that the Percent Complete Type (e.g. Duration, Physical, and Units) is set based on your requirements.

    2. Performance % Complete and Activity % Complete will be calculated depending on the setting of Percent Complete Type as mentioned in #1 above.

    Say for example your Physical % Complete is 35% then the Perecent Complete Type is set to Duration the 35% does not apply to your Performance & Activity % Complete. You need to change the Percent Complete Type from Duration to Physical in order to acquire the 35% based on Physical and this will apply to your Earned Value Labor Units.

    Cheers,

    Arnold 

  2. 0
    Abilash Palakkadan Mathew ·

    Thanks Arnold, This was

    Thanks Arnold,

     

    This was resolved earlier; anyway the summary is that ernd hrs is calculated from bq of baseline; when set the new baseline which includes new activities i have started to get earned hours.

     

    by

    Abilash