Primavera Import XER Problem

Evren CetinMember for 13 years 3 months
Created
5
2
0

Hi to All ;

I want to import xer file to P6 with all dates but ORGINAL DURATION , REMANING DURATION , SCHEDULE % COMPLETE , START and FINISH fields become empty . How can I import xer files with full information and updated status .

 

Thank you .

5 replies

Oldest first
  1. 0
    Alain De leon ·

    what is your version of p6

    what is your version of p6 and what is the version of xer file you want to import?

  2. 0
    Evren Cetin ·

    Both are same versions .

    Both are same versions . 7.0

    But when I try to import files they come with 0% progress .

  3. 0
    Evren Cetin ·

    Both are same versions .

    Both are same versions . 7.0

    But when I try to import files they come with 0% progress .

  4. 0
    Neil Hendry ·

    Hi Evren, Importing should

    Hi Evren,

    Importing should bring all these values in automatically,  see if you can get another copy of you XER file and try again.  (It may be a corrupt file)

     

    Regards

    Neil

  5. 0
    Ronald Winter ·

    Almost all data is exported

    Almost all data is exported when creating an XER.  There are no export options.  There are import options, however.  In the Update Project Options screen of the import XER operation, click on the Modify option button and review what you have selected to import.

    The only other possibility is that your P6 User ID is not authorized to import the missing data.  Check with your P6 System Administrator to confirm that you have the necessary authorizations.  Good luck!