Remaining early start

Jean DesjardinsMember for 14 years 11 months
Created
2
3
0

Hi everyone,

I have an activity that was completed earlier than planned (nov 1st instead of nov 8)

Meanwhile its successor remaining early start date remains on november 11th. (the data date is nov 1st)

Is there a way to advance the rem. early start to nov. 1st ?

The only way I found to resolve that is removing the link with the predecessor.

Jean

 

2 replies

Oldest first
  1. 0
    Kylee Foster ·

    Hi Jean, Is there incomplete

    Hi Jean,

    Is there incomplete logic link on the predecessor task?  This will still push the successor task even if the (first) predecessor is finished.  If you've time better to fix this than just deleting the link and it would change the successor task start date.  Careful with interproject links too if that is applicable.

    Regards, Kylee.

  2. 0
    Jean Desjardins ·

    Thank you Kylee,In the

    Thank you Kylee,

    In the schedule options I've checked "Progress override" instead of "Retained logic"

    Regards