Skip to content

Actual Cost's Are Not Distributing Correctly

Brook BolgerMember for 17 years 5 months
Created
1
1
0

I have a project where the actual costs are not distributed in accordance with the actuial dates for that activity. Instead, the costs are placed on the data date and cause a graph spike. this occurs when the "sort costs by financial period" option is turned off. Does anyone know what causes this? 

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Brook,I suggest 2 Things:1.

    Brook,

    I suggest 2 Things:

    1. Try to assign a resource curve on the Resource.
    2. Remove and Re-assing the same Resource.

     

    Regards,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?