Global Change to remove all logic/relationships to external projects?

V KuttyMember for 15 years 9 months
Created
1
2
0

Hi All

 

Just wondering if theres a way of removing all activity relationships to external projects via a global change?

 

Thanks for any pointers

 

V

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    go to the schedule options

    go to the schedule options and check ignore relationships to and from otherl projects

    also if you export this file to xer then import the file back in durign the importing porcess select modify and under the Data Type: Project section in the Relationships to external Projects you can choose DO NOT IMPORT