Actual Cost
In the Open Standard
Tom TomMember for 12 years 2 months
- Created
- 2
- 2
0
Hello All,
I am currently working on a cost loaded schedule. The client use schedule to justify our monthly billing. I am currenly using Physical Percent Complete for Earned Value calculation and we are able to calculated Earned Value to match our Pay App. My question is: Do I also need to input actual cost. I would think doing so would reveal to the client how much profit (or loss) my company makes. How do you usually handle actual cost? Since the hypothetical actual cost = Revenue - Margin, does it even make any sense to input actual cost into Primavera since since this will cause CPI to be always greater than 1