Calender ( HELP !!! )

Question AnswerMember for 12 years 8 months
Created
3
18
0

I actually need your help, How can i change my project Calendar ( Of Each activities ) from 10 hours to 8 hours without affecting the activities duration( Start & Finish date for each activities & the entire project ).i.e All activities will remain with the same start date & the same Finish date. My program initially should have a 8 h/day calendar but somehow i overlooked it and carried out on preparing my program based on 10 h/day calendar. Now due to the client’s requirement i have to change it to 8h/day calendar but i cant change the duration for activities as they have been agreed upon. I want the start date of each activities to remain the same likewise the finish date.

3 replies

Oldest first
  1. 0
    Tim Neobard ·

    Do you have resources as

    Do you have resources as well? If not, then you can do a global change.  Please make sure you backup a copy of the programme and baselines before doing this.  You will also need to manually extract the baseline.  If you do have resources etc, you will need to extract the programme to excel and manually change it there - I've personally not been in that situation as yet so I've not made a work around.

    10/8 = 1.25

    Therefore we need to divide all activities by 1.25.  But you cannot divide/multiple by fractions in P6 v8.2 (integers only, not floating point numbers).  Therefore we have to increase the original duration by a factor of 100 so that we can divide by 125.

    Under the 'Where' section, you need to save the remaining duration after the first calculation.  You need to use the {custom} field to allow you to do maths.

    I have used duration 1

    Line 1 of "Then" section of global change.

    Parameter:  Duration 1

    Is: =

    Parameter/Value: Remaining duration

    Operator: *

    Parameter/Value: {custom} (see below for value)

    custom in this case is 100

    2nd line

    Then

    Parameter: Remaining duration

    Is: =

    Parameter/Value: remaining duration

    Operator: /

    Parameter/Value: {Custom} set to 125

    Apply the global change

    You can now change the calendar to 8hrs and reschedule.

     

    Anyone got a better way of doing it, give me a shout I always like to learn new things...

     

    I've not played with changing units etc, but the below seems to work - I've bound to have forgotten something though...

    You could change subject area in the global change to 'activity resource assignments' (top left box when you've created a new global change) - don't forget to backup just in case and make sure you check it's applied properly before doing lots of major changes.

    Where (nothing)

    Then:

    Parameter: Number 1

    Is: =

    Parameter/value: Remaining units/time

    Operator: *

    Parameter/Value: 0.80 (numbers are floating point, durations are not)

    AND

    Parameter: Remaining units/time

    Is: =

    Parameter/Value: Number 1

     

    Should do the trick assuming you've not progressed anything.

  2. 0
    Tim Neobard ·

    <ignore this, repeated below>

    <ignore this, repeated below>

  3. 0
    Zoltan Palffy ·

    unless you are looking at the

    unless you are looking at the TIMES meaning what time an activity starts and what TIME an activity finishes it really does not matter becasue a 1 day activty starts on that day and finishes on that day it does not matter if you work 8 hours per day or 10 hours per day it is all still that same day. 

    Now the difference comes into play if you are using manhours to determine hoow many men that you need per day.

    if you are using the duration type of fixed duration/units time then all lyou have to do is to make sure that you have a calendar that is 8 hours then filter for all activiites then add a column for the calendar (under general) then assign the firat activity to that clanedar in the column then do a fill down for teh rmainder of teh activities. This assigns your activities to the proper calendar.

    The other thing that you need to do is to go to the project directory and and make sure that you project is highigthed click on the defaults tab and on the right had side choose the 8 hours per day calendar. This way any new activities added to the scheudle wil automatically be assigend to the correct calendar.

    if you are using an duration type that that determines your duration based on manhours then you have anotehr problem. 

Log in or join to reply