How to keep activity code when I copy project to other EPS

Nguyen To TanMember for 11 years 5 months
Created
4
3
0

Dear experts, 
For example, I have a project(A) inside EPS (1). The project (A) has some activities which I added activity code (Area A, Area B...). But when I copy project (A) to other EPS (2), i lost all activity code which I added in activity. When I copied project, I ticked on all option of primavera requirement. I also used 2 way for copying ( 1.directly copy project/2.I made project (B) inside EPS(2) open 2 projects (A) &(B), in WBS window of (A) I copied them to (B) ) but I still lost activity code with activity in project (B). Could you help me? Thank you

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    I suggests to use the Project

    I suggests to use the Project Activity Code instead of Global.

  2. 0
    Zoltan Palffy ·

    actrivity codes come with the

    actrivity codes come with the project unless 1 you do not have the rigths to export them and or 2 the person you gave the the xer to does not have rights to import them and 3 you can choose what and how you import codes. maybe your default setting is set to do not import codes

    you can modify what and how you want to import infromation

    during the importing process select modify and then choose to insert new activity codes

    to see detailed instructions see my link

    http://pmsite.com/forums/viewthread/3196/

  3. 0
    Nguyen To Tan ·

    Thank for your suggestion.

    Thank for your suggestion. But I think I already did same your way. I will show you something more clearly as below. And Could you explain more clearly?

    Copy Project Pic

    Activity Code I used Pic

  4. 0
    Zoltan Palffy ·

    the codes you are showing are

    the codes you are showing are global so they reside with the database not the project so they are already there. So I am not sure of what your problem is now