Percentage complete
In the Open Standard
Leighton RogersMember for 10 years 9 months
- Created
- 1
- 2
0
Hi all
Ill give you a scenario.
i have an activity which has 800 man hours budgeted for it and say i have done 400 hours is there any way i can add the hours in so it will change the physical % complete automaticly?
Sorry for the simple questions im new to this game.
regards
L8S
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?