Skip to content

Percentage complete

Leighton RogersMember for 10 years 9 months
Created
1
2
0

Hi all

Ill give you a scenario.

i have an activity which has 800 man hours budgeted for it and say i have done 400 hours is there any way i can add the hours in so it will change the physical % complete automaticly?

 

Sorry for the simple questions im new to this game.

 

regards

 

L8S

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    change the duration type to

    change the duration type to units 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?