Altering Budgeted Labour units
- Created
- 5
- 1
Hi all,
Im working on a project i did not build the schedule for. the two activities that started this week are both critical and we are on course to finish on time but the budget labour units for both activities is 1600 hrs we will complete it in around 900 roughley. When im putting this infor into excel for my S cure i just need the cumm planned and cumm actual. obviousley the planned labour has been over estimated but this does not look any good for my s curve when it says we should be at 8% and we are at 5%. is it just something that will have to be left or should i change if possible the budgetd labour units or has any one got any advise on what they would do?
Thanks for sll your help
Regards
Leighton
5 replies
Oldest firstLog in or join to reply