Manpower Histograms-Remaining Hrs and adjsuted for Productivities,
In the Open Standard
David WhiteMember for 10 years 8 months
- Created
- 1
- 4
0
Hi All,
1. Schedule is loaded for the Revised Budget Manhours; say 1000 hrs.
2. Progress is earned 10% so 100 hrs earned.
3. The remaining scope is 900 hrs.
4. Activity remaining duration is 10 days (10 working hrs per day) so remaining hrs will 90 hrs per day.
5. The histogram will show 9 guys per day.
6. Now if our Fcst PF is 0.5 then I will be need 18 guys per day.
How model this in P6 or we have to take it out in Excel to do it as every activity may have different fcst.
Till now I have been of the view that never load the ‘Actual hrs’ in the schedule only progress the earned hrs and the remaining hours spread out in fcst dates indicates the ‘Remaining Scope’ which once pulled into excel will be adjusted for Productivities to create the Manpower histograms.
Please share yoru ideas!
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?