Problem with reports in P6 R8.3.2

Tomasz SzłapaMember for 10 years 9 months
Created
1
3
0

Hey guys!

 

It's my first post here! I made small research and didn't find any answer on my problem.
I tried to print out report from P6 but the total row doesn't work. Any idea why the Total doesn't sum up?
 
Ofc I can export data to csv and then make a sum but it's a lot easier to print it directly.

1 reply

Oldest first
  1. 0
    Tomasz Szłapa ·

    Thanks for answer but It

    Thanks for answer but It didn't help. In the end I found the true reason, which now is pretty obvious to me..

    How to solve the problem?

    Just filter by resource type ex. Labor then all works fine! Here's proof:

Log in or join to reply