Mukunda YoganandaMember for 10 years 4 months
Created
3
1
0

is there any to aply the filter schedule % complete > Actual % complete

 

Thanks

3 replies

Oldest first
  1. 0
    David Kelly ·

    Strictly speaking, no.But

    Strictly speaking, no.

    But Schedule Performance index  (cost) or Scedule Performance Labour units  (eaned value/planned value) is what you want as long as the plan is resourced.

  2. 0
    Mukunda Yogananda ·

    Thank you david, Why this

    Thank you david, 

    Why this simple concept is not there? is they have any reason not to put this day to day requirement. 

  3. 0
    David Kelly ·

    the BIG problem with %

    the BIG problem with % complete is that there are four of them to worry about - Time, Cost, Resources or Earned value..... so first you would have to define what sort of % complete you are comparing.  Once you have determined that, it transpires there are better metrics for "ahead or behind" cost, "ahead or behind" quantity "Ahead or behind" time and "Ahead or behind"  earned value.

Log in or join to reply