convert P6 file to MSP file

Kamesh AvasaralaMember for 15 years 11 months
Created
3
4
0

hi,

when we export P6 file to MSP file it is not converting all data into MSP rightly , like Lag is not getting in MSP, Actual finish dates are not getting correct and % column also nopt getting right in MSP converted file from P6 can you explain the procedure of export in more details 

3 replies

Oldest first
  1. 0
    David Kelly ·

    The issue is that it does not

    The issue is that it does not work. For example MSP and P6 calculate lags differently. To do the job properly you need to buy software to do the conversion. Collabro's Legare for example.

  2. 0
    David Kelly ·

    The issue is that it does not

    The issue is that it does not work. For example MSP and P6 calculate lags differently. To do the job properly you need to buy software to do the conversion. Collabro's Legare for example.

  3. 0
    Zoltan Palffy ·

    have you tired exporting it

    have you tired exporting it to an xml file  ?