My previous actual units changes
In the Open Standard
Ahmed FaragMember for 10 years 3 months
- Created
- 0
- 3
0
Hi;
Can anyone help with the following.
My previous actual units changes everytime I update (Schedule Project). I'm Sure I Untick the mark next to "Recalculate Actual Units & Cost when duration % complete changes" at project level.
note:- the actual changes to be linear change (for ex. if actual units are 24 for 4 periods each period changes to be 6 units)
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?