Labour Requirement for Next Concrete Pour

Zahid ShaikhMember for 10 years 1 month
Created
1
1
0

My new Construction manager keeps asking me, in Next Week or Next Month we have planned These many Corewalls & Slab concrete casting. How much Carpenter,Steel fitter,etc. has been loaded in the programme for these slabs so I can plan the Manpower requirement for that work. He was probably getting this type of info in his previous company I guess.

I have been manually going into that activity and writing our the resource labour requiement by hand. Is there a way to Filter out the Resource by Resource name, if Not weekly atleast monthly labour requirement for the planned slab casting

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    create seperate resources

    create seperate resources they type of labor and the type of material being tracked

    assign both of there to each activity

    assign the proper units for labor it will be manhours

    for material it wil be based whatever the material is being installed CY of concrete, tons of steel etc

    if you do this for all of your activities you can select view resource usage profile and see how the units are forecated to be spend as the relate to time. 

     