Labour Requirement for Next Concrete Pour
- Created
- 1
- 1
My new Construction manager keeps asking me, in Next Week or Next Month we have planned These many Corewalls & Slab concrete casting. How much Carpenter,Steel fitter,etc. has been loaded in the programme for these slabs so I can plan the Manpower requirement for that work. He was probably getting this type of info in his previous company I guess.
I have been manually going into that activity and writing our the resource labour requiement by hand. Is there a way to Filter out the Resource by Resource name, if Not weekly atleast monthly labour requirement for the planned slab casting
1 reply