Tracing Activity in HUGE Project
In the Open Standard
Noah CowlesMember for 10 years
- Created
- 0
- 4
0
I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cumbersome. Does anyone know of an easy way to take 2 activities and run some sort of report to determine if they are linked?
And perhaps in a batch functionality...?