Skip to content

Tracing Activity in HUGE Project

Noah CowlesMember for 10 years
Created
0
4
0

I work with a P6 Portfolio that has over 36000 activities in it. What I am struggling to do is determine if activity "A" is associated with activity "Z" because there are sometimes 500+ predecessor/successor activities and the Trace Logic tool is cumbersome. Does anyone know of an easy way to take 2 activities and run some sort of report to determine if they are linked?

And perhaps in a batch functionality...?

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?