P6 Update Start & Finish Date Time problem
- Created
- 5
- 3
Hi All,
I have a problem about update my schedule. When I imported my actual dates from excel to primavera, I see my actual start & finish column shows 00:00 time format Even though my works time starts 08:00 and finish 16:00. This couses unexpected variance.
For Example Although my baseline start & Finish 10-oct-16 08:00 , 14-oct-16 16:00 my imported actual dates shows 10-oct-16 00:00 , 14-oct-16 00:00 and this couses "variance- bl1 finish date" column show "1d" variance
I want to find a way to fix this automaticly like global change or format change. I tried approximately 3-4 hours on it and I didn't get any result.
Plesae share me any idea of you about this.