% Planned complete

Nouraldin AlqudsiMember for 10 years
Created
5
3
0

Hello Dears;

When we do the monthly report, we usually send to the contractor a table showing the most important zones which have the activities of the project; showing in this table:

1- % Planned complete

2- % Actual complete

3- Variance; (Actual % - Planned %)

No problem with getting the actual %, my question is how to get the planned %

Please Help :)

 

Thank You,

5 replies

Oldest first
  1. 0
    Domingo Bonaobra ·

    Hi Nouraldi,To be able to

    Hi Nouraldi,

    To be able to show the % Planned Complete ( Schedule % Complete in Primavera ), you should maintain and assign baseline to your current schedule.

    Hope this helps.

     

  2. 0
    Nouraldin Alqudsi ·

    Hello sir;Does this picture

    Hello sir;

    Does this picture describe your answer?

    and why the WBS has no planned (Schedule) Percent ?

    or i should estimate it?

    Thanks for your help :)

  3. 0
    Domingo Bonaobra ·

    Hi Nouraldi,1. Yes, you got

    Hi Nouraldi,

    1. Yes, you got it.

    2. Seems your schedule was not resource loaded?

    Please let me know.

  4. 0
    Nouraldin Alqudsi ·

    Hi Sir,The resources are

    Hi Sir,

    The resources are loaded,

    Actually i tried the same on another project, and the percentages for the WBS's were calculated

    Is there any relation between kind of resource ( which i dont know what is it ) and the shedule % ?

    Best Regards

  5. 0
    Domingo Bonaobra ·

    Hi Nouraldi, Hope this will

    Hi Nouraldi, Hope this will answer more on your questions.. https://www.planacademy.com/primavera-p6-schedule-percent-complete-guide-2/ Good Luck!!!