Cost Loaded 6k activity Project Overhaul
- Created
- 2
- 3
I have a cost loaded project with approximately 6k activities on a USACE project. So all of my schedule modifications monthly have to be detailed and documented appropriately. I am using XER as my claimdigger program because it is cleaner than P6's. But my team has created a new project schedule with new WBS, revising approximately 2500 relationships, and adding 1200 activities. Originally, we did not intend to use this revised schedule as the final. But of course now, we want to merge the two, using the old as the base file. Does anyone have experience taking on a task like this? I just was open to hearing people's strategies and what worked, didnt work for you.