Why Finish Date and Successor Start Date of Activities are same ???
In the Open Standard
Muhammad BilalMember for 11 years 6 months
- Created
- 2
- 3
0
Dear Sir,
I have 1 Issue regarding calendar. I have made 5 Days/week calendar with hours 08 to 16:00. when assigned to Activities, the Finish dates of activities and start date of its successor are same means successor is not starting in new day.... However, i made changes in scheduling option relationship lag to 24 Hours calendar as well... here is the attached picture...
Kindly help me out this situation.
Thanks