Skip to content

Why Finish Date and Successor Start Date of Activities are same ???

Muhammad BilalMember for 11 years 6 months
Created
2
3
0

Dear Sir,

I have 1 Issue regarding calendar. I have made 5 Days/week calendar with hours 08 to 16:00. when assigned to Activities, the Finish dates of activities and start date of its successor are same means successor is not starting in new day.... However, i made changes in scheduling option relationship lag to 24 Hours calendar as well... here is the attached picture...
Kindly help me out this situation.
Thanks

2 replies

Oldest first
  1. 0
    Yalçın Güner ·

    You should check your

    You should check your activity's start and finish date time. Most probably your precedessor activity's finish time is same the successor's start time like that ( Predecessor's finish 01-Nov-16 0:00:00 AM Successor's start 1-Nov-16 0:00:00 AM)

     

    To fix this go edit menu and user preferences/date tab and check the 24 hour box then you ll see date time linked activities.

  2. 0
    Zoltan Palffy ·

    what is the TIME on your data

    what is the TIME on your data date it should be 8:00 am

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?