Best Practice For Assigning Formwork resource
In the Open Standard
Haytham SaadMember for 13 years 6 months
- Created
- 2
- 5
0
what is the best practice to assign Form work resource in p6, i assign as material and fill in the budget units / time, but hthe issue is using budget units/time when tracking by month read the Qty. of formwork Muliplied by the duration for every assign, so what is the best way to assign an track formwork in p6,thnxx all