Hi, 

Performance percentage completion: On updating the P6 Program of works monthly (Jan 2017 to Feb 2017)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?

Regards,

Jossef

2 replies

Oldest first
  1. 0
    Kannan CP ·

    Hi Mostafa,Make sure that

    Hi Mostafa,

    Make sure that your Total Budgeted Cost is not increased. Also check if the previous month progress for any of the activities is reduced, as a correction.

    Best Regards

    Kannan

  2. 0
    Mostafa Yousef ·

    Thanks alot Kannan. As you

    Thanks alot Kannan. As you said there was increment in the budget. 

     

    Problem is now resolved. 

     

    Thanks