How to calculate earned value based on duration in P6 (Earned days or weeks)

Mohamed RiyasMember for 17 years 7 months
Created
1
1
0

Dear Team,

 

Clould you kindly hwo to implement in P6 to monitor the progress based on earned duration value. I read an artical with regard to this if you want i can send you all. Please send your e-mail.

Reagrds,

Riyas 

1 reply

Oldest first
  1. 0
    David Kelly ·

    Mohamed, It is quite easy.

    Mohamed,

     

    It is quite easy. You simply apply a resource to each activity, with the default units per time period (simplest if this is 1) This can be done in one pass with the multiple-assign function. 

    Earned value can only come from resources in P6, but if the budget quantity is the same as the duration, then earned value becomes a function of Duration % complete.

    Issues:

    P6 only earns value from a baseline.  Be careful. 

    If there are "real" resources in the plan, you will need to price these at zero in order for them not to be included in the earned value calculations.