How to convert MPP file to XER or MPX

Anthony IbhawohMember for 13 years 2 months
Created
5
1
0

hello house,

please does anyone know how to convert mpp to xer or mpp to mpx,

as whenever i import mpp to xer on primavera, i get error message as such he does not import.

 

am using P6,8.2

is there a software or any way around this

 

thanks

tony

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you have several

    you have several options 

    option #1 

    Primaver has a mpp to mpx converter

    here is the link

     
    Option #2

    save the file as an MPX

    Option #3

    convert the file from an MPP to a PPR then from a PPR to and MPX

    here is the link for the free softwate 

    http://smartworks-mpp-2-ppr-converter.software.informer.com/4.0/

     

    So, here is the tool help you to convert MPP to MPX.

    https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

    Nowadays, Microsoft Project save file as MPP format. However Primavera allow to import file as MPX format.

    So, here is the tool help you to convert MPP to MPX.

    https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

  2. 0
    Anthony Ibhawoh ·

    thanks alot

    thanks alot

  3. 0
    Anthony Ibhawoh ·

    thanks alot

    thanks alot

  4. 0
    Zoltan Palffy ·

    no problem

    no problem 

  5. 0
    Zoltan Palffy ·

    I AM AMMENDING MY POST SINCE

    I AM AMMENDING MY POST SINCE A NEW PRODUCT HAS COME TO THE MARKET.

    NEW OPTION #1 USE XERTRANSFER UTILITY  

    https://xertransfer.com/ 

    option #1

    Primaver has a mpp to mpx converter

    here is the link

    https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing Option #2

    save the file as an MPX

    Option #3

    convert the file from an MPP to a PPR then from a PPR to and MPX

    here is the link for the free softwate 

    http://smartworks-mpp-2-ppr-converter.software.informer.com/4.0/

     

    So, here is the tool help you to convert MPP to MPX.

    https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

    Nowadays, Microsoft Project save file as MPP format. However Primavera allow to import file as MPX format.

    So, here is the tool help you to convert MPP to MPX.

    https://drive.google.com/file/d/0ByHnieTJNwKGdGVybE5LaElOcnM/view?usp=sharing

     

Log in or join to reply