An sterisk on start or finish date

Carmen ArapeMember for 22 years 3 months
Created
3
3
0

 

Hi All,

 

What does an asterisk shown on start or finish date of an activity mean??

I understood that this symbols comes up when the activity has a constraints date (any kind).

I have received an schedule with asteriks on start or finish dates without any constraints.

Appreciate any input,

Have a nice easter days,

Carmen

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    There another

    There another possibility 

    there is an external constraint meaning that this activity has a predecesor from a DIFFERENT PROJECT.  

  2. 0
    Carmen Arape ·

    Zoltan,Thanks, dank u well,

    Zoltan,

    Thanks, dank u well, gracias.

    That is the explanation... I am using the Construction schedule and contractor is building the CM commissioning schedule and making links...

    REgards

     

  3. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 