Percent Complete Type-Duration Type

Mike ReymortMember for 9 years 4 months
Created
1
1
0

I have been looking around for a good explanation on the percent complete type and duration type settings. I have a pretty good idea about how they work and when to assign what, but would love to have a direct explanation from someone who actually worked with them.

 

Thanks in advance,

 

Mike  

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    if you want to use earned

    if you want to use earned value you have to use for percent complete however this does not update the remaining duration or your actual units so you can run a global change

    where physcial % complete is greater than 0

    then duration % complete = physical % complete

     

    for duration type if you do not want you labor units determining your durations use fixed duration and units/time

    if you want your durations determined by the resource then use fixed duration & units

Log in or join to reply