Fix earned value at period end

Peter BarlowMember for 9 years 3 months
Created
6
2
0

Hello

Is there any way that when the data date is moved on and progress is updated that the earned value at previous period end remains fixed at what it was. For example, an activity that was 90% complete at year end will always have 90% earned at that date.

 

Thanks in advance.

6 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    tools store period

    tools store period performance

  2. 0
    Peter Barlow ·

    I have been advised to do

    I have been advised to do this but when the data date is advanced and the activities progressed the earned value at previous periods is still changed.

  3. 0
    Zoltan Palffy ·

    after the update is

    after the update is totally done select tools store period performance 

    make sure to set up your financial periods 

  4. 0
    Morne Johann Beeslaar ·

    I would hazard that the

    I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.

  5. 0
    Morne Johann Beeslaar ·

    I would hazard that the

    I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.

  6. 0
    Zoltan Palffy ·

    thats if you are using

    thats if you are using physcial % complete