An application event has been intercepted event code CNASF-2717-D

Vinit TholeMember for 9 years 2 months
Created
1
3
0

Hi Everyone,

Can anyone please help in providing solution for above Event Code in P6?

The above event code occured with I was Maintaining Baseline., Could not do any further assignment. Please help.

 

Thanks in advance.

Vinit

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    it appears that you ahve

    it appears that you ahve reached your 4 gb limit. This issue can be caused when you have reached the maximum database limit.  The database limit with SQL Server Express 2005 is 4 GB

    You can shirnk the database and the file and you can deleted some of your older projects. Before you delete them make xer files so you can access them later if need be. 

    to shrink the database

    Go to Start Programs Microsoft SQL server 2005, SQL Management Express Studio

    the sever name is the name of the computer \Primavera

    Authentication is SQL Server Authentication

    User name is sa

    password is Prima123Vera then click connect

    Expand the databases highlight pmdb$primavera

    rigth click and select Task

    then shrink 

    then database