Actual Start Woks before effective date

Dwi Jaka PrastyaMember for 14 years 5 months
Created
2
3
0

Dear All Master Primavera<

I am Prastya,  I am is newbie to used primavera P6 in my project and still to learn and explore for this software,

I have problem during making the schedule, because in my project now already start work but the owner not state the effective date yet

Actually at site already work, but I must to insert this actual date to schedule.

 

So How to setting this problem ? (like this picture)

Thanks

 

Regards

 

Prastya

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    got to projects directory and

    got to projects directory and change the planned start date of the project

  2. 0
    Dwi Jaka Prastya ·

    Mr ZoltonCan i email to the

    Mr Zolton

    Can i email to the simulation problem.

    Thanks,

     

     

    Prastya