P6 Activities with Steps Name / Status Export

Sam DsozaMember for 20 years 3 months
Created
2
1
0

Hi 

I would like to export activities with steps including step names and status of steps in to excel spreadsheet. While Actiivty steps export provides infor about steps completed, in progress, etc. I am looking more on the lines of exporting activities with activity steps listed in separate rows in a spreadsheet. Can this be done in P6?

Secondly, I have relationships tha hover from one wbs to another - is there anyway to identify activities where relationshop move from one L2 WBS to another.

TIA

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello Sam,I do not find a way

    Hello Sam,

    I do not find a way to answer your first question; exporting the 4 fields relating to steps only exports the number of steps in each category;

    to identify activities having a relationshio with an activity being in a different WBS node, you could use a Global Change to concatenate the Successor / Predecessor ID with the WBS in a user defined text field, and insert this UDF in the activities table

    Alexandre

  2. 0
    Sam Dsoza ·

    Alexandre,Thanks for your

    Alexandre,

    Thanks for your comment.

    It seems that "activity steps" export to excel feature was available in prior version. Not sure, if this feature was removed or its just that I cannot find it.

    I am not sure if  I follow your recomendation correctly but I will give it a shot. Its worth trying.

    Thanks

    Sam