Skip to content

Urgent Help Please

Adab AzeezMember for 10 years 3 months
Created
7
2
0
While scheduling my project, my schedule % complete value increases for few seconds on the screen and later it adopts the previous constant value. I mean my schedule % complete value is not changing. Any leads please?

7 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    dud you update teh schedule

    dud you update teh schedule ?

    if you did update it what % complete type are you using ?

    did you change the data date ?

  2. 0
    Adab Azeez ·

    I am using duration type.

    I am using duration type.
  3. 0
    Adab Azeez ·

    Yes I change the data date.

    Yes I change the data date.
  4. 0
    Sultan Salabat ·

    For Schedule % Percent

    For Schedule % Percent completion, Check following

    1. Make sure your data date is valid

    2. Your baseline must be assigned. 

    However, for WBS, cost must be assigned to activites.

    Check above points and schedule again by pressing F9.

  5. 0
    Sultan Salabat ·

    For Schedule % Percent

    For Schedule % Percent completion, Check following

    1. Make sure your data date is valid

    2. Your baseline must be assigned. 

    However, for WBS, cost must be assigned to activites.

    Check above points and schedule again by pressing F9.

  6. 0
    Adab Azeez ·

    I guess I have fixed it

    I guess I have fixed it now. For this I have taken the following three actions. Probably anyone of these three actions have brought me on the right track. 1. I reduce the price per unit of each resources to 1$/ unit. 2. Many of the equipments' last activities were not having successor . So I assigned a successor. 3. All of the equipment's first activity were sharing same predecessor despite of having internal links between them. So removed all the predecessor except few leading equipments. May anyone of the above worked for me. Thank you so much for your support.
  7. 0
    Zoltan Palffy ·

    EVERY activity in the

    EVERY activity in the schedule MUST have a successor except the last one. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?