How to Get Project Percent Complete
In the Open Standard
Ahmad ObeidatMember for 7 years 6 months
- Created
- 4
- 3
0
Good day,
I have just made a new revised program for the project
I have added new activities and loaded the material resources for the remaining activities (Concrete).
How I can calculate the project percent complete?? depending on what?
how P6 is calculating the schedule % complete and units % complete?
when i roll up for all the project it gives a schedule % complete ?? is this accurate or what?
Regards,
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?
