2 week look ahead
- Created
- 8
- 3
I am attempting to make a filter for a 2 week look ahead that shows the tasks and bars that are scheduled to be worked on during the 2 weeks. They may be start dates that equal the dd+2 weeks or in progress tasks or ones with resume dates that match the dd+2 weeks. I seem be able to use these in the filter but end up lossing some tasks or gaining some while rearranging the filter.
The Inprogress tasks seem to be the ones that add the task bar outside the 2 week window. Anyone out there got the secret formula or the easter egg.
Happy easter all
Thanks for the help in advance