Help- Copying P6 activities to MSP
- Created
- 5
- 4
I need help in copying the activities and their durations (including WBS names) from primavera p6 to MSP
I have tried exporting the P6 schedule into excel and then loaded it into MSP, but unfortunately none of the activities were grouped under the respective WBS (so I spent the day creating summary tasks in MSP and copy pasting the activties in each WBS). The problem is that the P6 schedule has over 3000 activities.
I have also tried simply copy pasting the activties from p6 into msp but that results in errors and when I ignore them, the entire shcedule is pasted as activities (no WBS/ summary tasks)
Is there a faster (smarter) way of doing this? perhaps im pasting it incorrectly?
please help!