Right-click export to Excel -> other layout doesn't give any activities

Mi MoMember for 7 years 7 months
Created
4
2
0

Hi everybody,

I have been searching for this everywhere, but no succes..

So I always had succes when I used the right-click -> export to excel option.

Now, I have saved some different layouts and when I use a different layout I get an Excel export without any activities.

It does show the title columns.

I tried different view-filters and by accident I had one activity already marked as 'in progress', now this one was shown in the dump.

 

Anyone any idea what the problem is?

4 replies

Oldest first
  1. 0
    Mi Mo ·

    Wait... It doesn't have to do

    Wait...

     

    It doesn't have to do with the righ-click methode.. It doesn't export at all.

    It is a 3 day lookahead filter, so I think it has someting to do with the date.

  2. 0
    Mi Mo ·

    I have DD+3D filter OR status

    I have DD+3D filter OR status 'in Progress'

    It works to get the right view in P6, but when I export to Excel it doesn't give any results.

  3. 0
    Santosh Bhat ·

    Why are you right clicking?

    Why are you right clicking? In your activity view, press CTRL+A to select all, then CTRL+C to copy to clipboard, then Past einto an Excel worksheet.

  4. 0
    Zoltan Palffy ·

    highlight them first then

    highlight them first then rigth click export to excel  