Manpower report

Ron BeecheyMember for 10 years 6 months
Created
4
1
0

Is there a method in P6 that I have missed to see by manpower count " task to fix it " takes 2 millwrights.   I can see the budgetted manhours but I was asked if I could (like in MSP) if I could indicate the number of trades people assigned to a task.   Have I just missed something.

4 replies

Oldest first
  1. 0
    Tom Boyle ·

    Ron,There may be better ways,

    Ron,

    There may be better ways, but I've used the "Calculate Average" option for the Usage profiles and spreadsheets - with "Base on Hours per Time Period" checked.  The corresponding unit of measure that I use is "LEM" for "labor equivalent men."

    Good luck, tom

     

  2. 0
    Rafael Davila ·

    (No subject)

  3. 0
    Ron Beechey ·

    Thanks Tom looks like that

    Thanks Tom looks like that will work for what we are doing.   Already well into the project and have made a productivity adjudtment ( lowering from 1 to .5 by adjusting durations ) so I'mnot sure how that effect the labour hours but we will see.

  4. 0
    Zoltan Palffy ·

    RonI do the same thing that

    Ron

    I do the same thing that Tom does