Curved Data Date - why? what? when? is it for?

John ReevesMember for 13 years 5 months
Created
2
4
0

I am used to seeing a straight data date line. Lately I been seeing curves data date lines, ie curved out around certain activities.  I assume this is from a setting, and after googling it with-out getting an easy answer I am asking you.  What does it represent?  Where is the setting for it?

2 replies

Oldest first
  1. 0
    John Reeves ·

    OK, not that hard to solve,

    OK, not that hard to solve, it is the "Progress Line" which overlays the Data Date line.  Obviously I didn't use it much prior.  I kind of assumed it was something like that but here is a confusing aspect.  I don't have a Baseline attached to that schedule - so how can it be telling me how ahead or behind the dates are - meaning how can the line be crooked?

  2. 0
    Zoltan Palffy ·

    click on the crooked progress

    click on the crooked progress line icon and it wil be a straigh line.

     

     