Visualizer R16.1 (X64) not working after upgrade to Windows 10

Catherine GrovesMember for 12 years 6 months
Created
1
3
0

 My company pushed a Windows 10 update. My P6 works fine but Visualizer will not launch. It is a standalone database on my computer. I ran a trouble shooter and it comes up incompatable. 

There are no error messages it just doesn't launch. I tried running in compatability mode with an earlier version of Windows but that still doesn't help.

Is there something I can do to fix this?

1 reply

Oldest first
  1. 0
    Catherine Groves ·

    Found the answer. Visualizer

    Found the answer. Visualizer needs Java 7 to run. Installed Java 7 in addition to Java 8 and everything runs perfectly.