Create a Filter that show activities with no baseline

Mike plannerMember for 15 years 8 months
Created
3
2
0

Hi, 

 

I want identify all the new activities i added to my original programme. 

In order to do that, i think i need to create a filter that shows all the activities with no baseline but i cannot find a solution. 

How do i create a filter that show all the activities with no baseline?

 

Thanks

Mike  

3 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Use a filter with condition

    Use a filter with condition "Where BL Project Start (or BL Project Finish) Equals" and leave the value field blank.

  2. 0
    Mike planner ·

    Thank you so much! Mike

    Thank you so much!

     

    Mike 

  3. 0
    Rafael Davila ·

    Also of interest is when I

    Also of interest is when I need to identify and show all activities in compared schedule but absent in current version.

    Absent-in-compared-schedules-Gantt