I'm hoping someone can help me.  I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.

 

Can anyone help?

2 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Heather,Use the top row of a

    Heather,

    Use the top row of a filter to change the statement from "all" to "any" and then you can have three rows like this

    Row 1) Finish is less than DD+2w (if you want two weeks from the data date, CD+2w if you want from the current date)

    OR

    Row 2) Activity Type = Start Milestone

    OR

    Row 3) Activity Type = Finish Milestone

  2. 0
    hhadley ·

    Thanks!!