Skip to content

Export of Baseline

Jithin KambhikanamMember for 15 years 6 months
Created
6
2
0

Hello Everyone,

 

I am using  P6.18.8.0 version.

When I export it in XER format, the baseline is not been exported.

when I export in XML format again the baseline is not exported.

Any solution to this.

Thanks

Jithin 

 

6 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Baselines are not exported to

    Baselines are not exported to those formats, you need to go MAINTAIN BASELINES>RESTORE BASELINES then export this restored project seperately. Remembe to then re-attach the baseline to the original project.

  2. 0
    Alexandre Faulx-Briole ·

    Hi,Santosh, it is possible to

    Hi,

    Santosh, it is possible to export baselines together with the current project in the xml export process; you may select the baseline you want to export

    I guess this option exists since P6 17.x at the latest.

    Alexandre

  3. 0
    Jithin Kambhikanam ·

    Hi Alex, I did export in XML

    Hi Alex,

     

    I did export in XML Format, but again its not exporting the baseline.

     

    And while exporting its asking if to include baseline and I have selected the baseline to be exported. But after exporting the and importing it to another machine I am not able to see the exported Baseline.

     

    Is it a settings issue of Exporting Machine or Importing Machine ?

     

    Thanks 

    Jithin

  4. 0
    Santosh Bhat ·

    Alexandre,Yes you are corect.

    Alexandre,

    Yes you are corect. Sorry, its been a long time since I've had to use the XML format.

  5. 0
    Alexandre Faulx-Briole ·

    Hi Jithin,are you working

    Hi Jithin,

    are you working stand-alone, or client-server? in this case, is it possible that you are not allowed to export baselines?

    I am using P6 stand-alone with a SQLite database, and exporting/re-importing the baselines works perfectly with the XML format

    Alexandre

  6. 0
    Jithin Kambhikanam ·

    Hi Alex, Ya its working. I

    Hi Alex,

     

    Ya its working. I exported a XML File and the baseline was in it.

    Thanks for the tip.

     

    Regards

    Jithin

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?