Hello All!
More help needed......
I'm trying to create a filter that I can use daily to do a vertical slice of just the activities that are happening on a specific day.
Here's what I have so far but I'm not sure what I'm missing:
Activity Status not equal to Completed
Start equals Dec 1
Finish is great than or equal to Dec 1
4 replies
Oldest firstLog in or join to reply