How can the Contractor claim certain production rate is real without disclosing the resource assignments and production data? In this regard I agree with Zoltan.
I would require the schedule to disclose the crew composition that is resource quantities and workloads, the crew production rate, the production quantity and units in a very visible way for all production activities.

Please note that resource hours/effort and resource quantity are not the same, it is a misconception that dividing effort by a common denominator will give you the quantities. Multiple calendars and the sharing of part-time resources make it difficult if not impossible to figure it out.
Under most contracts it is the Contractor who has entitlement to the Means and Methods; it is real not a perception, the Contract is king. This does not relieve the Contractor of his responsibility to deliver. The Client has his right to be informed, he has the right to question the submitted schedule and keep it on record, perhaps with a disclaimer note. With regard to questioning the schedule I agree with Mutang.
If Owner wants to keep control of the Means and Methods he can do so under the right contract type, for some projects it makes perfect sense.
Ideally the Contractor would realize there might be the need for some schedule adjustments but stubborn contractors do happen. If submitted schedule is unreasonable and Contractor does not make it right then time will show the reviewer was right and any claim from either party would require the schedule be revised, a SOP. In such case I would recommend the Owner to keep a Ghost Schedule of his own.
Ghost Schedule