UDF Field Formulas Not available in Ver 20.1

Casey FMember for 10 years 4 months
Created
3
2
0

Is anyone aware of the process for setting up formulas in P6 v. 20.1.  Its been a while since I utilized formulas in the system, and can't seem to find any correct instructions on how to complete this that references the newer versions. 

Following the UDF instructions of the Oracle websites gets tripped up at the first step as I am not able to select Formula as a data type in the UDF field. 

Is this possibly a permission thing? (I have admin superuser) I am thinking the process just changed with the version changed so any In-sight would be great! 

Thank you, 

Casey Fuhrmann

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    guess you will have to do the

    guess you will have to do the math

  2. 0
    Casey F ·

    Thanks Zoltan, I'm not sure

    Thanks Zoltan, I'm not sure how I posted this twice, and also don't know how to remove it.

  3. 0
    Zoltan Palffy ·

    no problem

    no problem