Actual Units of previous updates changes after every new updates
In the Open Standard
Jegede OlorireMember for 9 years 6 months
- Created
- 7
- 3
0
Hello Great Minds,
Thank you in advance for your assistance.
I observed that after every new progress update in P6, the actual units of past progress update changes. Please find below an example. In January update, the actual unit for activity A1020 is 64.77. After February Update it changes to 74.03, Is there some settings I need to activate or is it just a P6 problem. To solve the problem I use store period performance but I think there is a problem with my settings. Please your knowledge and experience is needed. Thank you again for your inputs.